The 2030 CAP target (33.2 GW) is shown as hollow markers on the right axis. At current build rates, the system reaches ~24.6 GW by 2030 -- a gap of 8.6 GW. Total capacity well exceeds peak demand, but much of it is intermittent (wind/solar), so the reserve margin line shows what firm/dispatchable capacity must cover.
Bars show current capacity (2025), realistic 2030 projection at current build rates, and the government's Climate Action Plan target. Only solar is on a trajectory approaching its target.
Detailed Breakdown
| Technology | Now (2025) | Realistic 2030 | Target 2030 | Gap | Status |
|---|---|---|---|---|---|
| Onshore Wind | 5.0 GW | 6.5 GW | 9.0 GW | -2.5 GW | Behind |
| Offshore Wind | 0.025 GW | 1.3 GW | 5.0 GW | -3.7 GW | Far behind |
| Solar PV | 2.0 GW | 6.5 GW | 8.0 GW | -1.5 GW | On track-ish |
| BESS (discharge) | 1.05 GW | 3.0 GW | 5.0 GW | -2.0 GW | Stalled |
| Data Centre Demand | 9.4 TWh | ~13 TWh | -- | -- | On track |
| EV Fleet | 196k | 400-500k | 1M | -500k+ | 35% behind pace |
"On track-ish" for solar reflects very fast recent growth (160% in 2 years) but the target is still ambitious. "Stalled" for BESS reflects a large pipeline on paper (10 GW) but only 83 MW under construction.
Why Planning Matters More Than Finance or Technology
Ireland's renewables shortfall is not caused by lack of investment appetite, technology cost, or grid capacity (though those are secondary constraints). The primary bottleneck is the planning system:
- Capital is available: Ireland has among the highest capacity auction prices in Europe, making projects financially viable.
- Technology is mature: onshore wind, solar, and BESS are proven at scale globally.
- Grid is constrained but expanding: EirGrid's investment plan addresses most network limitations by 2028.
- Planning is the blocker: long approval timelines (2-5 years), judicial review risk, and community objections delay or kill projects. An Bord Pleanala's backlog adds 12-18 months to many projects.
Until the planning system throughput increases significantly, announced pipelines (10 GW BESS, 7+ GW offshore wind) will remain largely on paper.
Supply-Demand Dynamics and Battery Economics
Wind Planning Approvals
717 MW approved in 2024 (full year), far less in Q2 2025 (annualised ~220 MW). Planning approval rate is falling, not rising, at exactly the wrong time. The pipeline is large but stuck.
Solar Deployment
160% growth in installed capacity over 2 years. 1.2 GW added in 2024 alone. Faster permitting (ground-mount solar is less contentious), smaller project sizes, and strong economics are driving rapid uptake.
BESS Construction
10 GW pipeline on paper but only 83 MW under construction. Large gap between announced/permitted and actually being built. Grid connection timelines and capacity auction uncertainty are the main causes.
Electricity Demand
Record peak of 6,024 MW set January 2025. Data centre moratorium lifted; new connections proceeding. EV fleet growing (slowly). Heat pump adoption increasing. Demand growth accelerating after a decade of relative stability.
Data Sources
- EirGrid AIRAA 2025-2034 (All-Island Resource Adequacy Assessment)
- Wind Energy Ireland
- SEAI (Sustainable Energy Authority of Ireland)
- ESI Pipeline Survey
- Cornwall Insight
- CSO (Central Statistics Office)