Research Tracker

Tracking all research activity, claims, verifications, and open questions for the Irish energy storage arbitrage feasibility study.

Topics
10
Claims Filed
39
Cross-Verifications
6
Summaries
10 / 10
Financial Model
ERRORS
Topic Grid
01

Wholesale Market

Summary
5 claims 1 verification
Conf: C1: 18 C2: 23 C3: 7
DAM spreads EUR 83-121/MWh; SDP live Nov 2025; DASSA May 2027
Open Questions (7)
  • Actual post-SDP revenue data for BESS operators (expected mid-2026)?
  • Exact DASSA auction clearing price levels and volume forecasts?
  • Granular half-hourly negative price counts for I-SEM 2024-2025?
  • CRM de-rating factors for batteries at 1h, 4h, 6h+ durations?
  • T-4 2029/30 auction results (scheduled 26 March 2026)?
  • Per-MW revenue decline estimate from DS3 to DASSA?
  • Round-trip efficiency assumptions used by Irish trading houses?
02

Household Tariffs

Summary
1 claim 0 verifications
Conf: C1: 38 C2: 17 C3: 13
Best spread 38.8c/kWh (Bord Gais EV); dynamic pricing Jun 2026
Open Questions (4)
  • How will dynamic tariff savings compare to fixed TOU rates once June 2026 launches?
  • Will fixed TOU tariffs continue or be phased out after dynamic tariffs?
  • Realistic daily cycle count for battery warranty impact?
  • Are there battery-as-a-service offerings emerging in Ireland?
03

Fees & Charges

Summary
1 claim 1 verification
Conf: C1: 22 C2: 9 C3: 2
D-TUoS EUR 26-29/MWh is biggest cost; reform NOT adopted
Open Questions (6)
  • VAT treatment of wholesale I-SEM transactions?
  • Specific DS3 base payment rates (EUR/MW/hr per service)?
  • Local authority rates, planning levies on BESS facilities?
  • Exact formula for SEMO Collateral Requirement Calculation?
  • Imperfections charge impact on self-supplying BESS operators?
  • Site-specific connection costs beyond EUR 7,000 pre-app fee?
04

Irish Precedents

Summary
0 claims (old structure) 0 verifications
Conf: C2: 65 C3: 12
730 MW operational; 10 GW pipeline; 83 MW under construction
Open Questions (7)
  • Exact Dunnstown (Strategic Power) current status -- grid connection?
  • Detailed DS3 contract values per project?
  • ESB Inchicore operational date confirmation?
  • Gore Street Portersdown operational date?
  • FuturEnergy Ireland Ballynahone (iron-air) construction timeline?
  • Neoen Curraduff appeal outcome (200+ objections)?
  • Arigna LDES / Lough Allen appeal outcome?
05

EU Regulation

Summary
0 claims (old structure) 0 verifications
Conf: C1: 56 C2: 27 C3: 5
Battery passport Feb 2027; SBESS carbon footprint Aug 2030
Open Questions (5)
  • Will Irish planning require Battery Regulation compliance evidence?
  • Has EN IEC 62619:2022 been listed as harmonised standard?
  • Exact PEF/PEFCR methodology for SBESS carbon footprint?
  • Minimum performance and durability values (delegated act pending)?
  • Insurance implications of the regulation for BESS coverage?
06

Supply & Demand

Summary
11 claims 2 verifications
Conf: C1: 2 C2: 9 C3: 2
Demand +45% by 2034; BESS saturates at 2-3 GW; Celtic Interconnector 2028
Open Questions (6)
  • What DASSA clearing prices will replace DS3 tariffs? (DS3 extended to Sep 2027 longstop per SEM-25-031; DASSA targeted May 2027)
  • Will the 83 MW BESS construction pipeline accelerate?
  • How much spread compression will Celtic Interconnector deliver?
  • Can Ireland's planning system deliver 700 MW/yr onshore renewables?
  • Will CRU data centre policy unlock or constrain the 5.8 GW pipeline?
  • At what installed GW does Irish BESS arbitrage become unprofitable?
07

Battery Costs

Summary
10 claims 1 verification
Conf: C2: 6 C3: 4
LFP cells $36-56/kWh; turnkey EU $101-120/kWh; 45% YoY decline
Open Questions (8)
  • Vendor-specific per-MWh pricing from CATL, BYD, Sungrow, Fluence?
  • Exact HS code classification for specific BESS configurations?
  • Ireland-specific BESS degradation field data?
  • O&M cost breakdown by project scale tier (10/50/100 MW)?
  • EVE Energy warranty terms (primary source needed)?
  • Irish BESS project finance debt margin / spread data?
  • Timeline of EU anti-subsidy investigation into ESS imports?
  • Impact of CATL/BYD Hungary factory ramp on EU pricing?
08

BOS & Inverters

Summary
5 claims 1 verification
Conf: C2: 2 C3: 3
Transformer 128-144 wk lead time; total $125/kWh ex-China
Open Questions (5)
  • Ireland-specific BESS installed cost data (UK proxy currently used)?
  • All-in landed cost of Chinese equipment in Ireland after CBAM?
  • Are 20 MWh frontier containers available for European markets?
  • EMS licence fees for 100+ MWh Irish projects?
  • Impact of R&S Group / Kyte Powertech acquisition on transformer timelines?
09

Land & Sites

Summary
4 claims 0 verifications
Conf: C3: 4
4-5 acres needed; EUR 20-25k/acre/yr lease; 12-13% planning refusal
Open Questions (7)
  • Actual transactional premium for land adjacent to substations?
  • Will the 2024 Planning (Stationary BESS) Bill pass, and what EIA thresholds?
  • MW threshold for mandatory SID classification for standalone BESS?
  • Is Lough Ree/Lanesborough 110kV viable for a BESS project?
  • Actual grid connection costs at varying distances from substations?
  • Impact of ECP-GSS bi-annual batch process on project timelines?
  • Ireland-specific setback and fire safety requirements?
10

Grid Connection

Summary
2 claims 0 verifications
Conf: C3: 2
ECP-GSS bi-annual batches; EUR 25k/MW MEC bond; 4+ year timeline
Open Questions (7)
  • Actual EUR/MW shallow connection costs for representative BESS sites?
  • Current network capacity charge rates for bond calculations?
  • CRU decision on charging/rebating methodology (FMP vs rebate)?
  • Actual ECP-GSS batch processing times vs legacy 6-12 months?
  • Pass-through costs in ESB Networks generator connection charges?
  • Impact of TUoS/DUoS reform proposals on BESS economics?
  • EirGrid ECP Constraint Reports for location-specific availability?
Open Questions Tracker
# Question Topic Priority Blocked
1 Actual post-SDP revenue data for BESS operators (expected mid-2026 at earliest)? Wholesale HIGH No
2 Exact DASSA auction clearing price levels and volume forecasts? Wholesale HIGH No
3 Granular half-hourly negative price counts for I-SEM 2024-2025 (requires SEMOpx data)? Wholesale MEDIUM No
4 CRM de-rating factors for batteries at 1h, 4h, 6h+ durations? Wholesale HIGH No
5 T-4 2029/30 auction results (scheduled 26 March 2026)? Wholesale MEDIUM No
6 Per-MW revenue decline estimate from DS3 to DASSA (Cornwall Insight models paywalled)? Wholesale HIGH Yes -- paywall
7 Round-trip efficiency assumptions used by Irish trading houses for Li-ion BESS? Wholesale LOW No
8 How will dynamic tariff savings compare to fixed TOU rates once June 2026 launches? Tariffs MEDIUM No
9 Will fixed TOU tariffs continue or be phased out after dynamic tariffs become available? Tariffs LOW No
10 Realistic daily cycle count for battery warranty (6,000-10,000 cycles; daily cycling ~3,650/10yr)? Tariffs LOW No
11 Are there battery-as-a-service offerings emerging in Ireland? Tariffs LOW No
12 VAT treatment of wholesale I-SEM transactions (Revenue.ie TDM inaccessible; tax advisor needed)? Fees HIGH Yes -- needs advisor
13 Specific DS3 base payment rates (EUR/MW/hr per service)? Fees MEDIUM No
14 Local authority rates, planning levies, or development contributions on BESS facilities? Fees MEDIUM Yes -- council query
15 Exact formula for SEMO Collateral Requirement Calculation? Fees MEDIUM No
16 Imperfections charge impact on self-supplying BESS operators? Fees HIGH No
17 Site-specific connection costs (beyond EUR 7,000 pre-app fee)? Fees MEDIUM No
18 Exact Dunnstown (Strategic Power) current status -- grid connection obtained? Construction start? Precedents MEDIUM Yes -- developer query
19 Detailed DS3 contract values per project (pricing not disclosed)? Precedents HIGH Yes -- commercially sensitive
20 ESB Inchicore operational date -- inferred "early 2022" unconfirmed? Precedents LOW No
21 Gore Street Portersdown operational date? Precedents LOW No
22 FuturEnergy Ireland Ballynahone (iron-air) construction timeline? Precedents MEDIUM No
23 Neoen Curraduff appeal outcome (200+ objections to ABP)? Precedents LOW No
24 Arigna LDES / Lough Allen appeal outcome? Precedents LOW No
25 Will Irish planning permissions require Battery Regulation compliance evidence? EU Reg MEDIUM No
26 Has EN IEC 62619:2022 been formally listed as harmonised standard under the regulation? EU Reg LOW No
27 Exact PEF/PEFCR carbon footprint methodology for SBESS (delegated act delayed)? EU Reg MEDIUM No
28 Minimum electrochemical performance and durability values (delegated act not published)? EU Reg MEDIUM No
29 Insurance implications of the EU Battery Regulation for BESS project coverage? EU Reg LOW No
30 What DASSA clearing prices will replace DS3 tariffs? (DS3 extended to Sep 2027 longstop per SEM-25-031; DASSA targeted May 2027) Supply/Demand HIGH No
31 Will the 83 MW BESS construction pipeline accelerate, or does revenue uncertainty keep it frozen? Supply/Demand HIGH No
32 How much spread compression (EUR/MWh) will Celtic Interconnector actually deliver? Supply/Demand HIGH No
33 Can Ireland's planning system deliver the 700 MW/yr onshore renewable additions needed? Supply/Demand MEDIUM No
34 Will CRU's data centre connection policy (March 2026) unlock or further constrain the 5.8 GW pipeline? Supply/Demand MEDIUM No
35 At what installed GW does Irish BESS arbitrage become unprofitable for new entrants? Supply/Demand HIGH No
36 Vendor-specific per-MWh pricing from CATL, BYD, Sungrow, Fluence (all proprietary)? Battery Costs HIGH Yes -- vendor quotes
37 Exact HS code classification and BTI for specific BESS configurations? Battery Costs MEDIUM Yes -- Revenue query
38 Ireland-specific BESS degradation field data (no study found)? Battery Costs MEDIUM No
39 O&M cost breakdown by project scale tier (10 MW vs 50 MW vs 100 MW)? Battery Costs MEDIUM No
40 EVE Energy warranty terms (inferred from industry norms; no primary source)? Battery Costs LOW No
41 Specific debt margin / spread data for Irish BESS project finance? Battery Costs HIGH Yes -- commercially sensitive
42 Timeline and likelihood of EU anti-subsidy investigation into standalone battery/ESS imports? Battery Costs MEDIUM No
43 Impact of CATL/BYD Hungary factory ramp-up on EU pricing and lead times? Battery Costs MEDIUM No
44 Ireland-specific BESS installed cost data (UK figures used as proxy)? BOS HIGH No
45 Realistic all-in landed cost of Chinese core equipment in Ireland (shipping, insurance, CBAM)? BOS HIGH No
46 Are 20 MWh frontier containers (Gotion, Tesla Megablock) available for European/Irish projects? BOS LOW No
47 EMS annual licence fees for >100 MWh Irish projects (vendor-specific)? BOS MEDIUM Yes -- vendor quotes
48 Net impact of R&S Group / Kyte Powertech acquisition on transformer procurement? BOS MEDIUM No
49 Actual transactional premium for land parcels adjacent to substations vs standard agricultural? Land HIGH Yes -- agent/solicitor
50 Will the 2024 Planning and Development (Stationary BESS) Bill pass, and what EIA thresholds? Land MEDIUM No
51 Specific MW threshold for mandatory SID classification for standalone BESS? Land MEDIUM No
52 Is Lough Ree/Lanesborough 110kV node viable and available for a BESS project? Land MEDIUM No
53 Actual grid connection costs for sites at varying distances from substations? Land HIGH No
54 How will the ECP-GSS bi-annual batch process affect project timelines? Land MEDIUM No
55 Ireland-specific setback and fire safety requirements (vs US/EU defaults)? Land MEDIUM Yes -- reg query
56 Actual EUR/MW shallow connection costs for representative BESS project sites? Grid HIGH Yes -- EirGrid query
57 Current network capacity charge rates used in security bond calculations? Grid MEDIUM Yes -- CRU/EirGrid
58 CRU decision on charging/rebating methodology (FMP vs. rebate)? Grid HIGH No
59 How will actual ECP-GSS batch processing times compare to legacy 6-12 month window? Grid MEDIUM No
60 Pass-through costs in ESB Networks standard generator connection charges? Grid MEDIUM No
61 How will TUoS/DUoS reform proposals (Energy Storage Ireland March 2025) affect BESS economics? Grid HIGH No
62 EirGrid ECP Constraint Reports showing location-specific grid availability? Grid MEDIUM No
Verification Status
# Claim Verified Source Topic Method Result
1 LFP cell prices ($36-56/kWh range, 45% YoY decline) Battery Costs Cross-referenced BNEF, BloombergNEF, CATL quarterly reports Confirmed
2 D-TUoS costs (EUR 26-29/MWh system services charge) Fees Verified against CRU tariff determination documents Confirmed
3 Transformer lead times (128-144 weeks Europe) BOS Cross-checked Wood Mackenzie, IEA transformer report Mostly Confirmed
4 Celtic Interconnector (700 MW, spring 2028 commissioning) Supply/Demand EirGrid project updates, EIB financing records Partially Confirmed
5 Market saturation threshold (2-3 GW for Irish system) Supply/Demand GB precedent extrapolation, Cornwall Insight forecasts Partially Confirmed
6 Financial model IRR (stated 5-6% base case, 11.4% original); NPV; investment recommendation Financial Model Independent reanalysis (21 Feb 2026), 6 parallel verification agents, cash flow reconciliation CRITICAL ERROR
Research Progress

Wave 1: Micro-Researchers

20 / 20
20 parallel micro-researchers dispatched. Each answered one specific question and wrote one claim file. All complete.

Wave 2: Summarizers

7 / 7
7 summarizer agents consolidated claims into per-topic _summary.md files. 10 total summaries (3 from Wave 1 + 7 new). All complete.

Wave 3: Cross-Verifiers

6 / 6
6 verification tasks completed. 2 confirmed, 1 mostly confirmed, 2 partially confirmed. Full independent reanalysis performed 21 Feb 2026 with 6 parallel agents: 75%+ factual claims confirmed, 0% contradicted. Critical financial model errors discovered.

Wave 4: Financial Model

CRITICAL ERRORS
CRITICAL ERRORS FOUND (reanalysis 21 Feb 2026): 50 MW / 200 MWh, 4-hour LFP BESS. Prior stated base-case IRR of 5-6% — actual IRR is NEGATIVE (-3.5%). Original 11.4% was inflated by ~5-6pp (augmentation double-counting). NPV: EUR -22.7M at 5%. D-TUoS = 41.1% of gross revenue. Recommendation: DO NOT INVEST — WAIT. Model requires complete rebuild.